Thursday, August 27, 2009
political corruption in nigeria
Wednesday, August 26, 2009
Tuesday, August 25, 2009
solar panel installation
| ![]() ![]() ![]() |
| ![]() |
|
GO Solar Company uses "FastJack" solar panel mounts to structurally attach solar panels to a roof. The mounts are secured before the new roof is applied. For existing roofs we utilize "TileTrac" mounts. |
![]() (a unique patent pending design) |
|
| ![]() |
|
Secure the mounts to the roof with stainless steel lag bolts. The roof on this house was brand new but looked sloppy, so a new layer was applied around the mounts. | ![]() |
|
Metal flashings were placed over the mounts and the layer of roofing was hot-mopped around the mounts. Metal rails are secured to the posts with 3/8' stainless steel bolts. | ![]() |
|
Next we install pre-assembled and hard wired solar panels in groups of 4. No "quick connections" are used on our wiring. This array holds 20 of a total of 40 Siemens panels installed. | ![]() |
|
After the solar panels were in place a layer of reflective roof coating was applied to the roof. The final step is to run the conduit to connect the panels to the inverter. | ![]() |
![]() |